60 man can do a work in 40 days. How long will it take 40 men to complete the same work?
Answer: 60 days
Explanation
Men days
60 : 40
40 : x
60/40= x/40, 40x= 60* 40
x= 40*60/40, x= 60
This question appeared in
Past Papers (9 times)
FPSC 5 Years Past Papers Subject Wise (Solved With Details) (1 times)
FPSC Past Papers (1 times)
Inspector Customs, Intelligence Officer Past Papers, Syllabus (2 times)
PPSC 5 Years Past Papers Subject Wise (Solved with Details) (2 times)
PPSC Assistant Past Papers PDF (1 times)
PPSC Past Papers (2 times)
This question appeared in
Subjects (2 times)
MATHS MCQS (2 times)
Related MCQs
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- 5 men can do a work in 50 days. How long will it take 3 men to complete the work?
- Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?