A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
Answer: 6 days
Explanation
A and B together can complete the work in 3 days, so their combined rate of work is 1/3 per day.
They work together for 2 days, so they complete 2/3 of the work.
B leaves, and A completes the remaining 1/3 of the work in 2 days. This means A's rate of work is 1/6 per day (since A completes 1/3 of the work in 2 days).
Now, we know B's rate of work is the difference between their combined rate and A's rate: (1/3 - 1/6) = 1/6 per day.
Since B can complete the entire work in x days, B's rate of work is also 1/x per day.
Equating the two expressions for B's rate of work, we get: 1/6 = 1/x --> x = 6
So, B alone can complete the work in 6 days.
This question appeared in
Past Papers (5 times)
PPSC 5 Years Past Papers Subject Wise (Solved with Details) (2 times)
PPSC Assistant Past Papers PDF (1 times)
PPSC Past Papers (2 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are:
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?
- Hamza can do a work in 15 days and Aslam in 12 days. If they work on it together for 4 days, the fraction of work that is left is________?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- Twelve children take sixteen days to complete a work which can be completed by eight adults in twelve days. Sixteen adults started working and after three days, ten adults left and four children joined them. How many days will they take to complete the remaining work?
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?