X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?

Answer: 10 days
Explanation

X can do the work in 20 days, so X's work rate is 1/20 of the work per day.

Y can do the work in 12 days, so Y's work rate is 1/12 of the work per day.

X works alone for 4 days, completing 4/20 = 1/5 of the work.

Y joins X, and together they complete the remaining 4/5 of the work.

Their combined work rate is (1/20 + 1/12) = 8/60 = 2/15 of the work per day.

Since they complete 4/5 of the work together, it takes them (4/5) / (2/15) = 6 days to complete the remaining work.

Adding the 4 days X worked alone, the total duration is 4 + 6 = 10 days.

So, the correct answer is: 10 days.

This question appeared in Past Papers (4 times)
PPSC 5 Years Past Papers Subject Wise (Solved with Details) (2 times)
PPSC Assistant Past Papers PDF (1 times)
This question appeared in Subjects (1 times)
MATHS MCQS (1 times)

Install this app on your device for quick access right from your home screen.