Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
Answer: 4 days
Explanation
Step 1: Work Done by One Man and One Child in One Day
16 men complete the work in 12 days.
Work done by 16 men in 1 day = 1/12
Work done by 1 man in 1 day = 1/12×16=1/192
24 children complete the work in 18 days.
Work done by 24 children in 1 day = 1/18
Work done by 1 child in 1 day = 1/18×24=1432
Step 2: Work Done by 12 Men and 8 Children in One Day
Work done by 12 men in 1 day = 12×1/192=12/192=1/16
Work done by 8 children in 1 day = 8×1/432=8/432=1/54
Total work done per day by 12 men and 8 children = 1/16+1/54
Taking LCM (16, 54) = 432,
27/432+8/432=35/432
So, work done per day = 35/432
Step 3: Work Done in 8 Days
Work done in 8 days = 8×35/432=280/432
Remaining work = 1−280/432=152/432
Step 4: Work Done After Adding 3 More Children
Work done by 3 children in 1 day = 3×1/432=3/432
New work rate per day = 35/432+3/432=38/432
Remaining days required = 152/432/38/432=4 days
This question appeared in
Past Papers (4 times)
ASF Inspector Past Papers (1 times)
ASF Past Papers (1 times)
FPSC 5 Years Past Papers Subject Wise (Solved With Details) (1 times)
FPSC Past Papers (1 times)
This question appeared in
Subjects (2 times)
MATHS MCQS (2 times)
Related MCQs
- Twelve children take sixteen days to complete a work which can be completed by eight adults in twelve days. Sixteen adults started working and after three days, ten adults left and four children joined them. How many days will they take to complete the remaining work?
- Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- 10 women can complete a work in 7 days, and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
- 12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?