Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
Explanation
We are given:
24 men complete the work in 16 days → 1 man's 1-day work = 1/24×16=1/38432 women complete the work in 24 days → 1 woman's 1-day work = 1/32×24=1/768
16 men and 16 women work for 12 days
Step 1: Work done by 16 men and 16 women in 12 days
Work done by 16 men in 1 day = 16×1/384=16/384=1/24
Work done by 16 women in 1 day = 16×1/768=16/768=1/48
Total work done in 1 day = 1/24+1/48=2/48+1/48=3/48=1/16
Total work done in 12 days = 12×1/16=12/16=¾
Step 2: Work remaining
Total work = 1
Work done = ¾
Work remaining = 1−3/4=1/4
Step 3: Additional men required
The remaining work must be completed in 2 days.
Let x be the number of additional men needed.
Work done by (16 + x) men in 1 day = (16+x)×1384(16 + x)
Work done in 2 days = 2×(16+x)×1384=142
Solving for x:
(16+x)×2/384=¼
16+x=1/4×384/2=384/8=48
x=48−16=32
The closest option is 36 men
Related MCQs
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- Twelve children take sixteen days to complete a work which can be completed by eight adults in twelve days. Sixteen adults started working and after three days, ten adults left and four children joined them. How many days will they take to complete the remaining work?
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?
- 12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- If a person A completes a work in 12 days and person B in 6 days and they start working together then In how many days they will complete the work?