Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?

Answer: 36 men
Explanation

We are given:

24 men complete the work in 16 days1 man's 1-day work = 1/24×16=1/38432 women complete the work in 24 days1 woman's 1-day work = 1/32×24=1/768 

16 men and 16 women work for 12 days

Step 1: Work done by 16 men and 16 women in 12 days

Work done by 16 men in 1 day = 16×1/384=16/384=1/24

Work done by 16 women in 1 day = 16×1/768=16/768=1/48

Total work done in 1 day = 1/24+1/48=2/48+1/48=3/48=1/16

Total work done in 12 days = 12×1/16=12/16=¾

Step 2: Work remaining

Total work = 1

Work done = ¾

Work remaining = 1−3/4=1/4

Step 3: Additional men required

The remaining work must be completed in 2 days.

Let x be the number of additional men needed.

Work done by (16 + x) men in 1 day = (16+x)×1384(16 + x) 

Work done in 2 days = 2×(16+x)×1384=142

Solving for x:

(16+x)×2/384=¼

16+x=1/4×384/2=384/8=48

x=48−16=32

The closest option is 36 men


This question appeared in Past Papers (4 times)
ASF Inspector Past Papers (1 times)
ASF Past Papers (1 times)
FPSC 5 Years Past Papers Subject Wise (Solved With Details) (1 times)
This question appeared in Subjects (2 times)

Install this app on your device for quick access right from your home screen.