5 men can do a work in 50 days. How long will it take 3 men to complete the work?

5 men can do a work in 50 days. How long will it take 3 men to complete the work?

Explanation

Formula: Men * Days = Work
5 * 50 = 250
Formula:  Men * Days = Work
3 * Days = 250
Days=250/3

Answer =83.33