If 8 people work for 60 days, how many days will it take for 6 people to complete the same work?
Answer: 80 days
Explanation
To solve this problem, we can use the concept of man-days:
8 people × 60 days = 480 man-days
Since the amount of work remains the same, we can set up an equation for 6 people:
6 people × x days = 480 man-days
To find the number of days, divide 480 by 6:
x = 480 ÷ 6
x = 80 days
This question appeared in
Past Papers (7 times)
ASF LDC, UDC Past Papers and Syllabus (2 times)
ASF Past Papers (1 times)
FPSC 5 Years Past Papers Subject Wise (Solved With Details) (1 times)
FPSC Past Papers (1 times)
Inspector Customs, Intelligence Officer Past Papers, Syllabus (2 times)
This question appeared in
Subjects (2 times)
MATHS MCQS (2 times)
Related MCQs
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- 6 person completes a work in 16 days, 8 people will complete the job in how many days.
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- 125 people can finish a piece of work in 120 days , find the no. of people required to finish this same work in 100 days .
- If 10 people complete work in 20 days, in how many days can 8 people complete the same work?
- Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?