6 person completes a work in 16 days, 8 people will complete the job in how many days.
Answer: 12
Explanation
Step-by-step explanation:
Let the number of days be x , then
As it is an inverse variation
6×16=8×x
(6×16)÷8=x (by transposing 8)
=12
This question appeared in
Past Papers (4 times)
FPSC 5 Years Past Papers Subject Wise (Solved With Details) (1 times)
FPSC Past Papers (2 times)
IB Assistant Director Past Papers (1 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- If a person A completes a work in 12 days and person B in 6 days and they start working together then In how many days they will complete the work?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- A completes a work in 12 days whereas B completes the same work in 24 days. If both A and B work together, the work will be completed in ______