A can complete a work in 20 days and B can do the same work in 30 days. Both A and B can complete the work together in ______ days.
Answer: 12
Explanation
To find the number of days A and B take to complete the work together:A's rate = 1/20 (work per day)
B's rate = 1/30 (work per day)
Combined rate = A's rate + B's rate
= 1/20 + 1/30
= (3 + 2) / 60
= 5/60
= 1/12
So, A and B together can complete the work in 12 days.
This question appeared in
Past Papers (6 times)
IBA STS 25 Years Past Papers Subject Wise (Solved) (2 times)
IBA STS Past Papers, Syllabus, Jobs (2 times)
JEST Past Papers (2 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are:
- 12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.