A is twice as good as B as a workman. A takes 30 days less than B. How many days does both complete the work?

Answer: 20 days
Explanation

A is twice as good as B, so A's work rate is 2 times that of B.

Since A takes 30 days less than B, let's assume B takes x days to complete the work. Then, A takes x - 30 days to complete the same work.

Since A is twice as good, A's work rate is 2 times that of B, so A completes the work in half the time it takes B. Therefore, x - 30 = (1/2)x

Solving the equation, we get x = 60 days for B and x - 30 = 30 days for A.

Since A and B are working together, their combined work rate is the sum of their individual work rates. So, the total work is completed in (60 * 30) / (60 + 30) = 1800 / 90 = 20 days.

Therefore, the correct answer is: 20 days

This question appeared in Past Papers (4 times)
PPSC 5 Years Past Papers Subject Wise (Solved with Details) (2 times)
PPSC Assistant Past Papers PDF (1 times)
This question appeared in Subjects (1 times)
MATHS MCQS (1 times)

Install this app on your device for quick access right from your home screen.