8 machines can do a piece of work in 10 days. How long will it take 16 machines to do the work?
مشینیں 10 دن میں ایک کام کر سکتی ہیں۔ 16 مشینوں کو کام کرنے میں کتنا وقت لگے گا؟
Answer: 05 days
Explanation
Let:
- M1 = Number of machines in the first case = 8
- D1 = Number of days taken in the first case = 10
- M2 = Number of machines in the second case = 16
- D2 = Number of days taken in the second case =?
The formula for inverse proportion is: M1 * D1 = M2 * D2
Substitute the values: 8 * 10 = 16 * D2 80 = 16 * D2
To find D2, divide both sides by 16: D2 = 80 / 16 D2 = 5
So, it will take 16 machines 5 days to do the work.
This question appeared in
Past Papers (3 times)
ASF Corporal Past Papers and Syllabus (2 times)
ASF Past Papers (1 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- If 16 machines do a piece of work in 4 days, then 8 machines will do the same job in:
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are:
- 10 machines complete work in 5 days, 5 machines would complete in ----------- days.
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- A and B can do a piece of work in 12 days, B can C in 8 days and C and A in 6 days. How long would B take to do the same work alone?
- 30 labourer's working 7 hours a day can finish a piece of work in 18 days, if the Labourer's work 6 hours a day, the number of Labourers required to finish the same piece of work in 30 days will be _________.
- A soap factory makes 600 units in 9 days with help of 20 machines. How many units can be made in 12 days with the help of 18 machines?
- A soap factory makes 600 cartons in 9 days with the help of 20 machines. How many cartons can be made in 12 days with the help of 18 machines?
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.