10 machines complete work in 5 days, 5 machines would complete in ----------- days.
10 machines complete work in 5 days, 5 machines would complete in ----------- days.
Explanation
10 machines * 5 days = 50 machine-days.
50 machine-days / 5 machines = 10 days