12 men can do a piece of work in 10 days. How many men would be required to do the same work in 8 days?
Answer: 15
Explanation
12 men × 10 days = 120 man-days
To complete the same work in 8 days:
120 man-days ÷ 8 days = 15 men
This question appeared in
Past Papers (9 times)
Junior Clerk Past Papers (1 times)
NEECA Past Papers and Syllabus (2 times)
PPSC 5 Years Past Papers Subject Wise (Solved with Details) (2 times)
PPSC Junior Clerk Past Papers and Syllabus (1 times)
PPSC Past Papers (1 times)
Senior Auditor Past Papers and Syllabus (2 times)
This question appeared in
Subjects (2 times)
MATHS MCQS (2 times)
Related MCQs
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are:
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- 30 labourer's working 7 hours a day can finish a piece of work in 18 days, if the Labourer's work 6 hours a day, the number of Labourers required to finish the same piece of work in 30 days will be _________.
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- 12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
- A and B can do a piece of work in 12 days B and C in 15 days C and A in 20 days then that numbers of days taken by A B and C together to finish the work are?
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- 125 people can finish a piece of work in 120 days , find the no. of people required to finish this same work in 100 days .
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?