Operating System Scheduling
Consider the Gantt chart of 3 processes (P1 = 0 to 16, P2 = 16 to 23, P3 = 23 to 30) using First Come First Serve (FCFS) scheduling. What is the finish time of P2?
Answer: 23
Explanation
Process P2 starts at time 16 and finishes at time 23.
Finish time is the time when the process completes execution in FCFS.
This question appeared in
Past Papers (6 times)
ETEA 25 Years Past Papers Subject Wise (Solved) (2 times)
KPK Teacher Past Papers SST PST CT TT PET (2 times)
Secondary School Teacher SST Past Papers, Syllabus, Jobs (2 times)
This question appeared in
Subjects (1 times)
COMPUTER (1 times)
Related MCQs
- Which scheduling algorithm uses a "time quantum" to allocate CPU time to processes?
- A takes 6 days less than the time taken by B to finish a piece of work. If both A And B together can finish it in 4 days, find the time taken by B to finish the work.
- What type of chart is good for single series of data ? Column Chart Line Chart
- The menβs marathon started at 10:00 hours, and the silver medalist took 5 minutes more than the gold medalist and crossed the finish line at 10:55 hours. How much time does the gold medalist take to finish the race?
- Please finish the task in time.
- Which type of chart use in time changing project?
- what type of chart is useful for showing trends or changes over time?
- He asked me to finish the work in time.
- If 1 day work = 1/20 then time required to finish the job (in depth)
- Ali gives the following percentage of his time to different subjects. He gives 10% time to Islamiat, 20% to Science, 20% to Urdu, 20% to Mathematics and 30% to remaining subjects. What is the angle of the remaining subjects on the pie chart?