A takes 6 days less than the time taken by B to finish a piece of work. If both A And B together can finish it in 4 days, find the time taken by B to finish the work.
Answer: 12
Explanation
Step -1: Finding the work done by A and B in a day.
Let B takes a total of x days to complete the work alone.
So as know that A takes 6 days less than B we can write that A takes
x - 6 days to complete the work alone.
Work done by B in a day = x1
Work done by A in a day = x−61
Step -2: Finding x .
As we know that A and B together complete the work in 4 days,we can write
x1+x−61=41
Taking LCM and solving we get,
x(x−6)x−6+x=41
x(x−6)2x−6=4
This question appeared in
Past Papers (3 times)
PPSC 5 Years Past Papers Subject Wise (Solved with Details) (2 times)
PPSC Past Papers (1 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- 125 people can finish a piece of work in 120 days , find the no. of people required to finish this same work in 100 days .
- 30 labourer's working 7 hours a day can finish a piece of work in 18 days, if the Labourer's work 6 hours a day, the number of Labourers required to finish the same piece of work in 30 days will be _________.
- A is twice as good as workman as B and together they finish a piece of work in 18 days. In how many days will B alone finish the work?
- A is thrice as good as B in work. A is able to finish a job in 60 days less than B. They can finish the work in ______ days if they work together.
- A can finish a work in 40 days. 5 is 255% less efficient then A. The number of days A & B will take to finish the work working together in nearly ≠ 3?
- A and B can do a piece of work in 12 days B and C in 15 days C and A in 20 days then that numbers of days taken by A B and C together to finish the work are?
- 250 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is ______?
- A and B can together finish a work in 30 days. They worked together for 20 days and then B left after 20 days. A finished the worked. In how many days A alone can finish the work?
- If 15 men do a piece of work in 8 days. How many men will finish it in 10 days?
- If 28 men can finish a work in 15 days, 21 men can finish the same work in___________?