If 28 men can finish a work in 15 days, 21 men can finish the same work in___________?

If 28 men can finish a work in 15 days, 21 men can finish the same work in___________?

Explanation

Time is taken by 28 men to finish the work = 15 days

Time taken by a man to finish the work 15 × 28 days

Time taken by 21 men = (15 × 28÷ 21

                                       = 420 ÷ 21

                                       = 20 days

**