If six people dig a well 200m deep in 15 days, the number of people that are required to dig the same well in 18 days is _____?
Answer: 5
Explanation
6 people dig a 200m well in 15 days.
To find the total work done in terms of "man-days":
6 people × 15 days = 90 man-days
Now, let's find the number of people required to dig the same well in 18 days:
Let x be the number of people required.
x people × 18 days = 90 man-days
x = 90 / 18
x = 5
This question appeared in
Past Papers (6 times)
IBA STS 25 Years Past Papers Subject Wise (Solved) (2 times)
IBA STS Past Papers, Syllabus, Jobs (2 times)
IBA STS Screening Test Bps 05 to 15 Past Papers and Syllabus (2 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- 125 people can finish a piece of work in 120 days , find the no. of people required to finish this same work in 100 days .
- If 9 person can finish a task in 5 days, then how many people are required to complete the same task in 3 days?
- If it takes 6 people 6 days to do a job. How many days would it take 2 people working at the same rate to do the job?
- 6 person completes a work in 16 days, 8 people will complete the job in how many days.
- People had not had food _____ days.
- If 8 people work for 60 days, how many days will it take for 6 people to complete the same work?
- In a camp of 36 earthquake victims, there is enough food for 20 days. If 12 more people come in, how many days will the food last?
- 15 men were hired to plough a piece of land in 10 days. How many more men will be required to do the same job is 3 days?
- If 10 people complete work in 20 days, in how many days can 8 people complete the same work?
- People of the older generation ______ over the good old school days.