Five men can prepare ten toys in six days working six hours a day. Then in how many days can twelve men prepare sixteen toys working eight hours a day?
Answer: Three days
Explanation
We will use the man-hour concept here to solve this problem Formula: (M1 × d1 × h1)/ W1 = (M2 × d2 × h2)/ W2 Where M, d,h, W are numbers of men, number of days, number of hours and work done respectively. Calculation: (M1 × d1 × h1)/ W1 = (M2 × d2 × h2)/ W2 ⇒ (5 × 6 × 6)/10 = (12 × d2 × 8)/16 ⇒ 18 = 6 × d2 ⇒ d2 = 3 ⇒ Number of days to make 16 toys = 3 days
This question appeared in
Past Papers (2 times)
FPSC Past Papers (1 times)
IB Assistant Director Past Papers (1 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- 39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, of same efficiency working 6 hours a day, complete the work?
- Twelve children take sixteen days to complete a work which can be completed by eight adults in twelve days. Sixteen adults started working and after three days, ten adults left and four children joined them. How many days will they take to complete the remaining work?
- 250 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is ______?
- Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
- Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly completely the work in?
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- 24 workers working 7 hours a day produce 4000 units in 30 days. In how many days 30 workers working 8 hours a day will produce 3500 units?
- 195 men working 10 hours a day can finish a job in 20 days. How many men will be employed to finish the same job in 15 days if they work 13 hours a day?
- A toy factory manufactures 28,550 toys in 25 days. How many toys it manufacture in 7 days?
- 12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.