What is the effect of using a higher discount rate on a project's NPV?
What is the effect of using a higher discount rate on a project's NPV?
کسی پروجیکٹ کے این پی وی پر زیادہ ڈسکاؤنٹ ریٹ استعمال کرنے کا کیا اثر ہوتا ہے؟
Explanation
The effect of using a higher discount rate on a project's NPV is to decrease NPV.
As it reduces the present value of future cash flows, making the project less valuable.
This is because a higher discount rate implies a higher opportunity cost of capital.