A project should be accepted if its internal rate of return exceeds _____?

A project should be accepted if its internal rate of return exceeds _____?

کسی پروجیکٹ کو قبول کیا جانا چاہیے اگر اس کی داخلی شرح منافع _____ سے زیادہ ہو؟
Explanation

A project should be accepted if its internal rate of return (IRR) exceeds the company's required rate of return.

This indicates that the project is expected to generate returns higher than the company's minimum acceptable return, making it a potentially profitable investment.