A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?

A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?

Explanation

 men completed the remaining job in .
Now the same job has to be done by .
We know that, 
Required time 
Delayed time