If a certain job can be performed by 18 workers in 26 days, the number of workers need to perform the job in 12 days is?

Answer: 39
Explanation

Work = Force x Time

Since the work remains the same, we can set up a proportion:

18 workers x 26 days = x workers x 12 days

To solve for x, we can cross-multiply:

18 x 26 = x x 12

468 = 12x

Now, divide both sides by 12:

x = 468 / 12

x = 39

So, the correct answer is: 39 workers