12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
Explanation
w = Men x Days x Hours
12 x 8 x 10 = 960
960 / 8 x 15 = 8 Men