A carpenter lays x bricks per hour for y hours and then lays x/2 bricks per hour for 2y more hours. In terms of x and y, how many bricks did he lay in total?

A carpenter lays x bricks per hour for y hours and then lays x/2 bricks per hour for 2y more hours. In terms of x and y, how many bricks did he lay in total?

Explanation

In the first y hours, the carpenter lays xy bricks.

In the 2y hours thereafter, he lays (x/2)(2y) = xy bricks.

Altogether, that's xy + xy = 2xy bricks.